Project concept and added value
The Konotop–Romny Cluster is one of the three waste management clusters in Sumy oblast identified in the Regional Waste Management Plan. The project provides for the construction of a single high-tech complex for municipal solid waste management in Konotop city hromada.
This comprehensive regional solution will address existing waste management challenges in the two largest rayons of the oblast. It will reduce adverse environmental impacts and the environmental risks associated with waste management, bring the waste management system into line with EU standards, and help preserve a protected natural area of local significance.



What problems does it solve? What do we strive for?
Geography and cluster infrastructure
The facility will be located on a 15.34-hectare land plot allocated for the project near the city of Konotop, more than 70 km from the border with the Russian Federation, which helps reduce security risks. The complex is designed to serve 267,000 residents across 16 territorial hromadas, about a quarter of the population of Sumy Oblast.
Cluster structure:



Engineering equipment of the waste management complex
The design capacity of the complex is 80 thousand tons/year.
The total capacity of the landfill is 1.54 million m³, which provides for environmentally safe operation for 19.6 years.
Functional areas of the complex
Expected impact of the project
Project readiness and institutional contacts
A land plot with an area of 15.34 hectares has been allocated for permanent use. The design and estimate documentation have passed all necessary procedures, a positive conclusion from the Environmental Impact Assessment has been received, and the construction project has been registered in the DREAM system (code DREAM-UA-240724-D3C38C3B).
Total estimated cost: UAH 1,320,311.8 thousand
Construction works: UAH 739,301.2 thousand
Equipment, furniture and fixtures: UAH 264,547.5 thousand
Other costs: UAH 316,463.1 thousand
Construction duration according to the project is 34 months.